Okaloosa County, Florida – A $40.8 million infrastructure project is taking shape in north Okaloosa County, bringing a major expansion in wastewater treatment capacity that could help determine how the area grows in the years ahead.

The numbers tell a big part of the story. The new Shoal River Water Reclamation Facility will initially treat 1.25 million gallons of wastewater daily, but its design leaves room for a much larger operation capable of handling up to 15 million gallons per day in the future.

Okaloosa County recently shared a construction update on the facility, which is being built within the Shoal River Industrial Park. Officials say the project remains on schedule, with substantial completion expected by the end of 2026.

The numbers tell a big part of the story. The new Shoal River Water Reclamation Facility will initially treat 1.25 million gallons of wastewater daily, but its design leaves room for a much larger operation capable of handling up to 15 million gallons per day in the future.
Credit: Okaloosa County

Read also: Drivers face new access roads and turning restrictions near Brooks Bridge

The facility is being constructed on 20 acres of designated property at Shoal River Ranch. Once operational, it will provide wastewater treatment services using modern technology, along with on-site disposal of treated wastewater.

One of the project’s most important benefits involves residential development.

New subdivisions in this part of Okaloosa County will have the opportunity to connect to public sewer infrastructure instead of relying on individual septic tanks. That change will provide another utility option as development continues across the northern portion of the county.

The facility is also being designed with long-term needs in mind.

Although its starting treatment capacity will be 1.25 million gallons per day, the infrastructure will allow future expansion to between 10 million and 15 million gallons daily.

The numbers tell a big part of the story. The new Shoal River Water Reclamation Facility will initially treat 1.25 million gallons of wastewater daily, but its design leaves room for a much larger operation capable of handling up to 15 million gallons per day in the future.
Credit: Okaloosa County

Read also: Downtown Fort Walton Beach invites families to a holiday market that ends with the lights on

Another planned feature involves reclaimed water. The project includes infrastructure that could eventually make treated water available for irrigation and industrial operations, creating additional possibilities for water use as the surrounding area develops.

The $40.8 million investment extends beyond the treatment plant itself.

Construction includes a new access road and extensions of water, sewer and fiber lines needed to serve the facility and support surrounding infrastructure.

Funding comes from several sources, including federal and state grants and a state legislative appropriation.

Meanwhile, work has begun on another major component of the area’s water infrastructure.

Crews have started construction of a 500,000-gallon elevated, pedestal-style water tank along the facility’s driveway. The same location will accommodate a future water well, which is currently in the design phase.

Read also: Fort Walton Beach firefighters launch ninth Christmas toy drive to help local children

According to the county’s latest update, the wastewater facility should reach substantial completion before the end of December 2026.

However, that milestone will not mean the entire operation immediately reaches full capacity. Officials anticipate another two to three months in early 2027 before the facility becomes fully operational.

Together, the wastewater treatment plant, new water tank and additional utility connections represent a substantial investment in the Shoal River Industrial Park and the infrastructure needed to accommodate future residential and industrial growth in north Okaloosa County.