Drivers face new access roads and turning restrictions near Brooks Bridge

Fort Walton Beach, Florida – A major change is underway for drivers crossing Brooks Bridge, where a $171 million replacement project has reached one of its most important milestones. For the first time, westbound traffic is moving onto the newly constructed bridge structure, bringing motorists a step closer to a completely rebuilt crossing over Santa Rosa Sound.
The switch is only the beginning. More traffic changes are coming, and drivers traveling between Okaloosa Island and Fort Walton Beach will need to pay close attention to new access roads, turning restrictions and nighttime construction activity.
The new traffic pattern began taking shape last week along U.S. 98 westbound, between the Destin-Fort Walton Beach Convention Center on Okaloosa Island and Perry Avenue in Fort Walton Beach.
Read also: Downtown Fort Walton Beach invites families to a holiday market that ends with the lights on
To prepare for the transition, construction crews temporarily reduced traffic to one lane in each direction during nighttime operations. Westbound vehicles were then directed onto the new bridge structure.
New traffic pattern changes how drivers cross Brooks Bridge
Under the current configuration, westbound U.S. 98 traffic uses the newly built westbound bridge, while eastbound vehicles continue crossing the original Brooks Bridge.
Despite the ongoing construction, all four regular travel lanes remain available, with two lanes operating in each direction.
However, accessing Santa Rosa Boulevard now requires drivers to follow different routes depending on their direction of travel.
Westbound motorists heading toward Santa Rosa Boulevard must take the new connector road located west of the Destin-Fort Walton Beach Convention Center and continue toward the roundabout.
Drivers traveling north on Santa Rosa Boulevard who want to enter U.S. 98 westbound must pass through the signalized intersection, continue to the roundabout and follow the new connector road and access ramp onto the bridge.
Eastbound motorists face another important restriction.
Left turns from U.S. 98 eastbound onto Santa Rosa Boulevard northbound are no longer allowed under this configuration. Drivers must continue east and use the designated connector road instead.
Pedestrian access remains available along the sidewalks on the south side of the existing bridge, beside the eastbound travel lanes.
Construction signs will guide motorists through the changes.
More traffic shifts and bridge demolition are coming
The current arrangement is expected to continue for several weeks before another major transition takes place.
During the next phase, eastbound traffic will also move onto the newly constructed westbound structure.
Once both directions are using the new bridge, construction crews can begin demolishing the existing crossing and building the new eastbound structure.
Motorists should also prepare for occasional nighttime lane closures along U.S. 98 between Ferry Road and Pier Road.
These closures may occur Sunday through Thursday, from 9 p.m. until 5:30 a.m.
Read also: Fort Walton Beach firefighters launch ninth Christmas toy drive to help local children
A six-lane bridge is expected by early 2029
The $171 million project will ultimately replace the four-lane Brooks Bridge, which opened in 1966, with two parallel bridge structures providing six travel lanes.
Construction is currently scheduled to finish in early 2029.
Weather could affect that timeline for individual construction activities, with work potentially postponed or rescheduled during unfavorable conditions.
For now, transportation officials are urging drivers to slow down, follow posted signs and remain alert, particularly during nighttime operations when workers and construction equipment may be entering or leaving the roadway.
The first new structure is carrying traffic, but the larger transformation of Brooks Bridge is still underway.